 |
 |
 |
Above--Kurt
Kelley buried by Baxter on the Cat Stabilizer/Reclaimer
while mixing fly ash.
Above Left--_Emmet Frese in the
Backhoe and John Cleppe in the Trencher, Tama
Co.
Left--Jeremy Rucker in
the Trencher
Bottom Left --Kevin
Fowler on the Shoulder Machine and Brian
Morrison installing outlets.
Bottom--The Wirtgen
Stabilizer/Reclaimer being pulled out near the
Jordan Creek Mall |
 |
 |
Well another season is coming to a close. At the
time of writing this article we need an additional 3
weeks to finish subdrain with 2 crews running. That
finish date runs right up to Christmas if mother nature
will hold off the rain and freezing temperatures. The
season was pushed back with all the rainfall this year
and several projects grew substantially with added work.
The added work isn't a bad thing unless your schedule is
all ready full. This is what happened and is now pushing
us to the limit on construction. I realize this puts the
crews in some nasty weather conditions at times, but
hope we can finish before the real cold stuff comes in.
Its a tough business when you have to deal with working
outside. I hear it every year, early spring and late
fall sucks due to the weather. Attitudes go south and
tempers grow short. This is the time you need to step
back, take a minute to think and then move on. Working
this way distracts you from the task at hand. This is
how safety incidents rise because of not being aware of
your surroundings.
The Sealcoat / Stabilization crew has had a full
year and then some. Over all the total amount of
sealcoating was down some, but we had several projects
tied with stabilization that filled the voids. 22,000
tons of fly ash were mixed into various projects this
season. A couple of the larger projects were completed
in Tama County 12,215 ton and Jasper County using 6620
ton. This process is gaining very good results in
sub-standard subbase materials and more engineers are
looking to use fly ash for next year. This crew also has
the equipment to inject asphalt emulsions as a
stabilizing agent and the city of Jefferson contract was
one such project that doubled in size after it was
started. A total of 182, 000 gallon was mixed into the
existing sealcoat streets.
After they parked the sealcoat equipment around the
first of October, they jumped on the second set of
subdrain equipment to help Bob and his crew's schedule.
They moved around Jasper, Lee, Davis and currently
Benton County to install subdrain. If the weather holds
and they can complete Benton County they will have
helped place 152,500 feet of subdrain.
Next year has a large grading and stabilization
project in Jasper County on the books. It is in several
of the small towns that the county is responsible for
the road maintenance. It involves pulverization of the
existing roadway and then stabilizing with fly ash. This
will take around 8,000 ton if locations allow and cover
a work period of at least 2 months. Another large
project that will cover a month is down at Lake
Thunderhead in Missouri. It is approximately 20 miles
south of Centerville on highway 5. It involves 14 miles
of lake roadway to add rock, some fly ash work and then
double sealcoat.
Bob and his crew have just steadily trenched all
season with a few shoulder stone projects thrown in. As
usual this means covering all corners of the state. They
too have had some projects grow in size after the
initial contract. It added an additional 120,000 feet to
a full schedule. They kicked out April 12th and I hope
they can be done by Christmas also. Looking back at
production records, the month of August stands out as
they placed 158,000 feet in one month! As of December
4th they have placed 864,158 feet. Combining what the
sealcoat crew has placed and what both crews are to
finish this month will make a total for the year at
1,078,081 feet! This kind of volume has not been seen in
along time. Next years schedule already has a good start
to it as we have an approximate 275,000 feet on the
books.
I would like to take this time to thank each and
everyone of my crew members for a great year! It is a
great pleasure to set up a project and the county or
state says " we won't have much inspection staff here
because we are short handed and we know your guys are
the best there is in the state! If there is anything
that needs to be changed just do it, we know it will be
right! " I get this time and again for these crews. We
still have to improve our safety incidents, they are
down, but they should not even exist. Once we get the
equipment parked and you are at home for the winter,
take care of yourselves and families so when can all
return next year. We still have a crew member
recuperating at home. Ken Souer is on the mends and we
hope you are ready for next year! Have a Merry Christmas
and Happy New Year! |