|
All the plants that don’t have hot water
capabilities have closed just one short week after many
of them had monster days. A few of the plants have had
an average to below average year, but most of them have
been very busy. Overall in the North, we are well ahead
of last year’s yardage mark.
Oelwein is having the best year ever, a year
that has surpassed all expectations. Oelwein has been
working all summer on an ethanol plant between Fairbank
and Oelwein. We have already supplied over 14,000 cubic
yards to various contractors on the project. Included
in that yardage was a 60-hour non-stop slip form pour of
a pair of silos. Oelwein has five drivers stationed
there and the slip pour required three trucks around the
clock, so outside help was needed. Waterloo drivers
Jake Simon & John Mummelthie were joined by United
driver Harold Kavailer to take on the night driving
duties on the pour. Harry Ritter, an Oelwein driver,
batched the plant during the nighttime hours. Hats off
to these guys! It is very tough to shift from working
days to working nights. Also, I want to thank Eric
Brashaw, Newhall manager, for his help on the slip
pour. He stayed in Oelwein for the week and helped haul
concrete during the day.
Last week we supplied the footing pad for the next slip
form pour. The first trucks were on the job at four in
the morning. The contractor wanted trucks as fast as he
could get them to feed his two pumps, as well as trucks
dumping directly into the hole. There was some concern
on if we could supply them fast enough since it is
roughly a 20-minute haul from both Jesup and Readlyn and
ten minutes from Oelwein. Waterloo, Denver &
Independence sent their trucks loaded to the project and
then they were dispersed to Readlyn, Jesup and Oelwein
to finish out the project. The pour was 1300 cubic
yards and was basically finished by ten in the morning,
which is very fast considering that at two of the three
plants they have to double or triple batch. We used
over 30 mixers including drivers from Oelwein, Jesup,
Independence, Readlyn (Mike Watson), Denver, Waterloo,
Products, Vinton & seven trucks from United Concrete.
We had as many as 8 trucks unloading at once. Thanks to
all that participated in the pour, everyone was safe and
did a great job. There is another slip form pour
scheduled for the third week of December that should
take five days. In addition to Oelwein being busy with
the ethanol plant, the guys there have also been
supplying a new wastewater treatment plant and a
downtown renovation-paving project. We passed the 2004
yardage total in July and will be busy in Oelwein
through December. It has been an amazing year in
Oelwein, hats off to Danny and all the drivers there.
In
addition to Oelwein, the Independence plant has had a
great year as well. A Super Wal-Mart store and a few
paving jobs have kept the Indy crew busy and they are
well on their way to a near record year. The new plant
in Grundy Center has had a great year for Jerry. Jerry
adapted very quickly from pulling levers and triple
batching to pushing buttons to batch on his computer.
Grundy Center has supplied a large paving project and
numerous residential projects. Grundy will finish the
year well ahead of last year’s mark. The yardage in
Readlyn has almost doubled last year’s total. This is
largely due to a subdivision-paving project in town.
Readlyn has also been the backup plant to Oelwein for
much of the ethanol plant project, and has supplied many
yards there. David Demuth has stepped in and managed
the Readlyn plant for us in Dale’s absence. David had
to triple batch on the ethanol pour last week, delivered
from 20 minutes away, and still supplied almost 200
cubic yards. David has done a great job for us. Traer
is substantially up from last year as well. Vernon
supplied two paving projects in town as well as many hog
confinements. Hank in Jesup has had an excellent year
in just his first full year as a manager. Jesup is well
ahead of last year. Some projects Jesup has been
supplying are an addition on Bertch in Jesup, numerous
IDOT projects and helping out with the ethanol plant.
Hank had to double batch on the big pad pour at the
ethanol plant last week, had to deliver from 20 minutes
away, and still supplied over 400 cubic yards to the
project.
Denver and La Porte City both had great years last year,
which are hard to match. That being said the yardages
are down at these two plants. Denver has been helping
the other plants out and has been supplying mostly
residential projects. There is a paving project that
will begin first thing in the spring in Denver, which
should get the year started nicely. La Porte City
supplied some IDOT projects throughout the summer and
has helped the other plants out many times. There is a
new aquatic center going in La Porte City, but the
majority of that concrete will be supplied by Waterloo
during the winter.
The Waterloo total should be about the same or slightly
higher than last year. Some projects that Waterloo has
supplied include a new Hy-Vee on the North side of
Waterloo, a new elementary school in Cedar Falls, the
Cedar Falls street reconstruction project, a large
addition to VGM and a large paving project across the
street at John Deere. The Waterloo drivers have also
been busy helping out the surrounding plants on a
regular basis.
Chas Wagoner, the Waterloo dispatcher, had been asked to
and agreed to step up and take on more duties in sales.
Chas has been calling on the Waterloo customers and
going to the plan room on a regular basis. He has
readily accepted his new duties and adapted easily.
Mike Watson (sales) and Dave Distler (QC) have been very
busy this summer and are often asked to be at two places
at once. Their abilities and knowledge are major assets
to us.
We
have seen some changes in our value added products
(expansion, fiber, chemicals), and had to find new
suppliers. We have established an inventory for these
products in Waterloo and Mike is dispersing them around
to the plants. Carolyn Hotzel is keeping close tabs on
the inventory and doing a great job with it.
Thanks to all the employees that have made this year
such a success, your good work does not go unnoticed and
it is greatly appreciated. Keep up the good work and
please continue to work safely. May everyone have a
safe and happy holiday season. |