1775 Old 6 Road
PO Box 535
Brooklyn, IA 52211
Phone: 641-522-9206
fax: 641-522-5594

Menu
 
Company 
Services   
Employment 

 

 

 


   

 

 

 


 

 

   

 

The high for today is going to be in the 90's as I write this. Summer is officially here! Hopefully, we have broken the three day a week rains. All three divisions have full schedules for the season and we don't need any more rain delays. We are doing pretty good for our safety incidents, but we need to strive for the zero incident level every month! I am happy to see everyone wearing 

their safety vests as required. I know they may feel a little warmer with them on, but it is notintolerable and it is better to be seen than being ran over!

Bob and the Subdrain crew started out on April 4th and haven't looked back since they left the yard. To date they have roughly installed 249,960 feet. Some of the areas they have covered have been in Tama, Black Hawk, Benton, Marshall, Lee, Muscatine, Marion, and Polk counties.

One project of interest is with Des Moines Asphalt who has the contract to resurface the main runway at the Des Moines International airport. Everyone had to go through a security screening, be finger-printed, and take a half day safety class to work on the facility. Safety has been increased since the 9-11 attacks.  It’s sad that even in the middle of Iowa, we have to take these measures to protect ourselves from the lunatics of the world.

The project is very labor intensive as the tile is in 20' lengths and the entire trench backfill has to be wrapped in fabric. Bob has been pulling his hair out as most of the plan design doesn't match what is out there. He has been doing a lot of field design on the go. I get a lot of compliments on this crew and Bob's leadership. This is one of those projects where his and the crew's talents shine. 

I also have to give an "att-a-boy" to the trucking crew that follows Bob, as I have been told they show respect to other contractors on the project and watch out for safety concerns of others.  Way to go guy and gals! 

This crew has roughly 545,000' left on the books. I would like to pick up an additional 200,000 in the next couple of months and they would have a full season. We have been lucky in the last few lettings to keep adding around 50,000' each month.  Hopefully this trend will continue and we'll fill the schedule out.

Where do I start with the Sealcoat and Stabilization crews. This crew shows their talents as they bounce back and forth doing stabilization projects and keeping the sealcoat projects on schedule also. The big project is Jasper County, as they are fly ash stabilizing the existing old sealcoat streets in 14 small towns across the county. With the design help of Mike Olson, the Jasper County Engineer, this project is going very well.

The crew first moves in and pulverizes and sizes the existing street. Minor grading changes are done at this time. The county then hauls in and spreads a layer of 3/4" road stone on this surface. (See Pic A)  The fly ash is then spread on top of this with the spreader trucks. The Wirtgen reclaimer then blends the material with additional water for compaction. (See Pic B)  Following this is the motorgrader and rollers for compaction. (See Pics C, D, & E) Mike is very pleased with the final out come of this base material. He has told me this crew has come a long way in working this project. He can't be any happier with the way they have been handling the possible dusting problems, cleaning the project up as they go and taking a true pride and commitment in the product they are turning out. I have to say this crew has really stepped up to the plate and is showing their growing talents!

Their schedule is full for the season.  For this reason, we have hired 7 new crew members to assist and are splitting them into 2 crews to cover the work load. For those of you who have been here a while, take the time to make sure the new people understand the equipment they are on and why they are doing a certain process. Understanding the entire project or process can make things a lot easier to do if you know what you are trying to accomplish. The other very important issue is safety.  Don't assume they know just because they are on the crew. Train and explain!

These 2 crews have now moved down to Lake Thunderhead to do an approximate one month project of  sealcoating the entire roadway system at the lake. This will involve some fly ash stabilization, tear up and relay of existing roads, spreading 4,000 ton of road stone for leveling, then priming and double sealcoating. Along with this is the growing number of driveways to also grade and cover. From there, they will catch up on sealcoating and Jasper County again as the culvert and grading work is completed. After that is the Hamilton County foamed asphalt stabilization project that should take around 4 weeks to complete. We will need 70 degree weather through October for as much work as we have to complete!

For all the crews, continue to work safely and watch out for your fellow crew member. Keep up the high degree of quality work that you are all capable of. We have a lot of work to finish, but it won't take long if we do it all right the first time!