Things
are really busy in
the
Newton
area. Virg and his
guys have
been at the track placing
some
rock. The asphalt at the
track will
probably get going
around the
second week of June. Mike Viehdorfer should be
placing the footing for the safety barrier.
Once that is in place Virg will be following
right behind with rock. As soon as the rock is
in place and trimmed, the portable crew should
be there and waiting to do the asphalt.
Another thing going on in Newton is a new shop
and office building. Henningson Construction
out of Atlantic is the general on this project.
When it gets a little farther along we can have
some pictures for the next newsletter.
The portable crew has been working in Poweshiek
County so far this season. They have been
resurfacing Hwy 6 from Hwy 63 N to just East of
V18. They will be finishing the intermediate
lift this week and be starting the surface
layer. We are sure hoping that one more layer
will smooth it up. This is the first job we are
doing using the zero blanking band. We will be
able to give the verdict in the next newsletter. |