1775 Old 6 Road, PO Box 535, Brooklyn, IA 52211-0535 USA
Phone: 641-522-9206
fax: 641-522-5594

Menu
 
Company 
Services   
Employment 

 

 

 


   

 

 

 


 

 

                  

What's 'News' in Ames?
Don Stevens

    

    Looks like another fall is upon us.  We have been busy this year, hard at work trying to complete a lot of projects before school started.  We were in a crunch for the last month prior to the start of school to complete a myriad of projects around town that had to be open by the time the students started back up. 

    Some of the projects we’ve completed were a parking lot for the Ames High school, 20th Street which was a collector street to the Ames high school, a parking lot in Ogden for Howe and North Middle school, Ames Roosevelt school, and the Gilbert schools. 

    John and Randy Hugen and his crew were the main force behind getting most of these projects completed.  Most of these projects were completed well before school started, but there seemed to be more than a fair share that were started late this year. 

    The 20th street project for the city of Ames collector program was started just after the bid letting on the second week in August. We were required to completely replace 5 blocks of this street before August 31, 2001.  The reason the city wanted this street opened up quickly is because this stretch of 20th Street is the main access road to the Ames High School.  This project had over 5400 sy of seal coat and rock removal, 1048 lf of concrete curb & gutter removal and replacement, 2100 tons of 6” crushed asphalt base, and 2770 tons of 11” hot mix asphalt street paving.  We were able to open 20th street up just one week after school started as per the required completion.

    Another project that we’re just completing is for Story City.  This project was awarded at $208,850.00 and had 60 days to complete.  Brad Lenz with the help of Mark Lamer and his crew completed the majority of the work well within the 60-day time frame.  They were responsible for removing and replacing a block of Story City’s downtown sidewalks and work on two other streets.  The new sidewalks joint pattern was quite involved and took some coordination and time.  This crew did the majority of work on this project and even delved into some grading for new parking areas at the local park.

    Right now we’re in the middle of working on the Ames Airport.  This project was awarded at $817,110.00 and started July 24 with a scheduled completion by September 21.  So far we’re on schedule and starting on the second phase of work to complete the project. 

    We used Newton’s mill to remove approximately 4200 ton of asphalt. These millings were used for the 9” and 11” sub base under the asphalt.  Then we installed over 3000 ton of asphalt for the new taxiways.  Steve Rooney and his crew graded the taxiways to very tight tolerances to allow the asphalt crew to do their job.  With our new foreman Craig Kalinay’s, the asphalt crew, and with the help of Duane Hassebrock, they were able to install the asphalt under very strict guidelines.

    Cindy De La Rosa and Tim Peterson have been very busy making sure that the special asphalt mix performs to the tight specifications required by the FAA.  Joel Clayton and his crew installed over 5000 lf of sub drain along the edge of the new paving and Jeremy Holland out of Brooklyn was able to put the finishing touches on the project by finish backfilling the edges for us.

    On the sidelines, Shellie Johnson in the office is asking for information because she doesn’t have all the phase codes so the guys can get paid.  

    Also, Brian Peterson and the maintenance department have been keeping us operational.  I might mention that Larry and Brian Frame with ready mix have been supplying concrete for us also, but that’s another story.

    This year we don’t have as much work as we have in the past two years.  However, the work is still coming in and it seems we’re busy as usual.  Thanks to the hard work of the Manatt’s people, we’re looking at having another successful year here in Ames!

 
updated by Jamie (9-12-01)




    

Record Day on V18

Brad's News

South Ready Mix

Golf Outing
Wedding News
The Final Push
End of Year Repair
PCC Paving
Ames - Tom Manatt
MIS Happenings
Health Insurance
Information
Creative Problem Solving Saves Day
Claims Reminder
HR News
Stork Club
Ames - Don Stevens
Safety
Computer News
Trenching Subdrain Stabilization
In Sympathy
Quality Control
Understanding Insurance Better
Welcome to Parts
Relay for Life
Newton News
Trucking
Salsa Contest
Environmental Update
RAGBRAI Thanks
BGM Playground Project
Wendling News
This ~N~ That