1775 Old 6 Road, PO Box 535, Brooklyn, IA 52211-0535 USA
Phone: 641-522-9206
fax: 641-522-5594

Menu
 
Company 
Services   
Employment 

 

 

 


   

 

 

 


 

 

                  

Trenching/Subdrain/Stabilization
Dave Schinckel

    

    The summer season finally kicked into high gear! Just as I said earlier, "we'd go from worrying about what we are going to do?, to worrying how we will get it done!" I'm not complaining because it’s a lot better worry, than nothing to do!

     Virg and the sealcoat crew have been running full-bore keeping ahead of completion dates. They had a good-sized project in Muscatine County involving stabilization of one county park road and several miles of sealcoating. The county engineer decided to add several miles of stabilization work to this contract and quickly added another 7 days to a full schedule.

    From there they moved to Rathbun Lake and had that project doubled! The schedule grew by 2 weeks and I didn't really have the room to push it, but you can't really move away and come back.

    At the time of this letter they are getting the second rain delay in Cerro Gordo county. This is not a good thing when completion dates are still counting down and you are not on that project.

    One of those projects is for Jefferson county. It is a stabilization project using calcium chloride and then applying a double sealcoat.

    As we are getting behind, I went hunting for some good help and was able to borrow Dick Prusha and a couple of hands from the milling division. Thanks a ton to those guys and the milling department for the assistance!

    We have a large stabilization project in Jasper county yet to complete and I'm sure they will be called upon again, if their schedule allows.

    At the present, I see the sealcoat crew working up to the 2nd week in October. That is a lot longer than I like to see them go because of problems with cooler temperatures.

     Ending with that statement, takes me into the stabilization work left to do.

    Kurt has been bouncing all around doing several jobs for L.L.Pelling on the east side of the state.

    He just finished incorporating Fly-ash into the sub-base at the Chariton airport for the PCC division and then moved to Jefferson county to scarify the existing road in preparation for the calcium work. The major project still waiting is the Jasper county work. The dirt contractor on the project is several weeks behind from his original estimate of completion.  I'm sure this project will push the envelope on cold weather on trying to complete as much as possible. If the entire project was ready, it would take 14 days to complete. Last estimate to have 3 to 4 miles ready, put it right at the end of the month or first of October. I'm sure this project will have a lot of carry over for next year. If the fall comes in early and wet, I'm sure we will be getting some calls to incorporate Fly-ash into sub-grades to keep projects out of the mud.

    Subdrain work is starting to level out from the first overload of several projects being completed at the same time. At the time of this letter, Bob and the crew are down on Highway 92, between Oskaloosa and Knoxville. This project involves the shoulder widening of the existing roadway, subdrain, and then being overlaid with asphalt. Cessford construction of LeGrand is the prime contractor on this project.

    The interesting part of this project is the removal of the 2' widening unit. It is presently PCC concrete. Cessford is doing the removal of the concrete, then the subdrain crew comes thru, followed by Cessford backfilling the trench with asphalt and then opening back up to traffic that evening. This project is about 13 miles long and gets subdrain continuous, both sides. Its a good thing they have that many miles to work in, because when you get all of the crew's equipment and trucks bringing material in and out, it takes that much area to set up traffic control! There is 140,000 feet to install so they will be there awhile. Production was slow at first, but it is coming together and they have been able to install 9000' per day if all of the situations come together.

    At the present time, contract work should keep this crew busy through October.

    I have heard that this winter is going to be pretty much the same as last year. If that's the case, it will snow early and stay on the ground for a long time. I'm hoping it isn't too early so we can still get a full season completed with the unusual late start this spring. If there is any truth to the old wives tale of when you hear the locusts start to sing, it will frost around the last week of September from when I heard the first bug tuning his song up. Hopefully, it will be well into October for that!

    As the fall push swings into action, we need to take time for safety. Taking a shortcut of a second or two can cost hours, if not days, of lost time.We've got a good season going and let's end it accident free! 

    Remember school is in season!  Watch out for the kids and school buses stopping on the roads. Cooler weather is coming so make sure to start checking anti-freeze levels. Also check tire pressures regularly as  ambient temperatures change, so do tire pressures! 

 STAY FOCUSED!  WORK SAFE!  HAVE A LITTLE FUN ALONG THE WAY!

   
updated by Jamie (9-12-01)




    

Record Day on V18

Brad's News

South Ready Mix

Golf Outing
Wedding News
The Final Push
End of Year Repair
PCC Paving
Ames - Tom Manatt
MIS Happenings
Health Insurance
Information
Creative Problem Solving Saves Day
Claims Reminder
HR News
Stork Club
Ames - Don Stevens
Safety
Computer News
Trenching Subdrain Stabilization
In Sympathy
Quality Control
Understanding Insurance Better
Welcome to Parts
Relay for Life
Newton News
Trucking
Salsa Contest
Environmental Update
RAGBRAI Thanks
BGM Playground Project
Wendling News
This ~N~ That