Since your web browser does not support JavaScript, here is a non-JavaScript version of the image slideshow: View at the Start/Finish Line from the Suites future location. This was taken on the day Robinson Services were installing the deep subdrain. The fill over the tunnel to the center track area had not yet been started. Pictures by Dave Schinckel Digital Splicing & Retouch by Sandy McAntire A view looking west towards the future grandstand from the upper RV parking area. Pictures courtesy of the Teen Track Tracker- - “Smoke” MillsDigital Splicing & Retouch by Sandy McAntire View at the Start/Finish Line from the Suites future location. This was taken on the day Robinson Services were installing the deep subdrain. The fill over the tunnel to the center track area had not yet been started. Pictures by Dave Schinckel Digital Splicing & Retouch by Sandy McAntire Floor pours for the infield buildings have started and the steel super structure for the Suites has begun to raise from the ground. Pictures by Dave Schinckel Digital Splicing & Retouch by Sandy McAntire The Suite’s super structure is approximately three quarters complete. To the left, the infield Care Center’s steel frame has been erected. To the right, work has begun on the Driver Meeting/Media Center framework. Pictures by Dave Schinckel Digital Splicing & Retouch by Sandy McAntire The Suites Super Structure is now complete. Framing has started on the Competitors Garage. Bob Kalinay & his crew are laying subdrain in the lower RV Camping area. Pictures by Dave Schinckel Digital Splicing & Retouch by Sandy McAntire Bob Kalinay ‘s Trenching Crew and Virg Heishman’s Sealcoat & Stabilization Crew. Subdrain is being installed along the bottom edge of the track. Base rock is being placed by Virg’s crew. Pictures by Dave Schinckel Digital Splicing & Retouch by Sandy McAntire View just north of the Suites looking down on pit row. Pictures by Dave Schinckel Digital Splicing & Retouch by Sandy McAntire The PCC Division started the footing for the Crash Barrier System Safety Wall. Base rock is being applied to the front straight away through turn 4 and into turn 3. Pictures by Dave Schinckel Digital Splicing & Retouch by Sandy McAntire The base rock application has been completed for the entire track. The next phase will be to finish grade the ten inch layer of rock followed by placing a five inch layer hot mix asphalt pavement Pictures by Dave Schinckel Digital Splicing & Retouch by Sandy McAntire All infield buildings are nearly enclosed. The Grandstand footings are starting to be visible in front of the Suites. Pictures by Sandy McAntire Digital Splicing & Retouch by Sandy McAntire
View at the Start/Finish Line from the Suites future location. This was taken on the day Robinson Services were installing the deep subdrain. The fill over the tunnel to the center track area had not yet been started. Pictures by Dave Schinckel Digital Splicing & Retouch by Sandy McAntire
A view looking west towards the future grandstand from the upper RV parking area. Pictures courtesy of the Teen Track Tracker- - “Smoke” MillsDigital Splicing & Retouch by Sandy McAntire
Floor pours for the infield buildings have started and the steel super structure for the Suites has begun to raise from the ground. Pictures by Dave Schinckel Digital Splicing & Retouch by Sandy McAntire
The Suite’s super structure is approximately three quarters complete. To the left, the infield Care Center’s steel frame has been erected. To the right, work has begun on the Driver Meeting/Media Center framework. Pictures by Dave Schinckel Digital Splicing & Retouch by Sandy McAntire
The Suites Super Structure is now complete. Framing has started on the Competitors Garage. Bob Kalinay & his crew are laying subdrain in the lower RV Camping area. Pictures by Dave Schinckel Digital Splicing & Retouch by Sandy McAntire
Bob Kalinay ‘s Trenching Crew and Virg Heishman’s Sealcoat & Stabilization Crew. Subdrain is being installed along the bottom edge of the track. Base rock is being placed by Virg’s crew. Pictures by Dave Schinckel Digital Splicing & Retouch by Sandy McAntire
View just north of the Suites looking down on pit row. Pictures by Dave Schinckel Digital Splicing & Retouch by Sandy McAntire
The PCC Division started the footing for the Crash Barrier System Safety Wall. Base rock is being applied to the front straight away through turn 4 and into turn 3. Pictures by Dave Schinckel Digital Splicing & Retouch by Sandy McAntire
The base rock application has been completed for the entire track. The next phase will be to finish grade the ten inch layer of rock followed by placing a five inch layer hot mix asphalt pavement Pictures by Dave Schinckel Digital Splicing & Retouch by Sandy McAntire
All infield buildings are nearly enclosed. The Grandstand footings are starting to be visible in front of the Suites. Pictures by Sandy McAntire Digital Splicing & Retouch by Sandy McAntire