Improving infrastructure one phase at a time
Altoona, IA
PCC Paving
1183 Cubic Yards of Paving
May 2026
As the first phase of a larger development along SW 32nd Street, the project includes constructing new roadways, sidewalks, and supporting infrastructure that will connect future housing developments and improve access throughout the area.
By building the foundation for future growth, the project is helping prepare the community for continued residential expansion.
1183Cubic Yards of Concrete
112Truckloads Delivered
2 DaysProject Duration
The team coordinated the installation of concrete pavement, stormwater intakes, curb ramps, and sidewalks to create the foundation for future development. Through careful planning and communication, work progressed smoothly while maintaining quality throughout each stage of construction.
Scope of Work:
The first phase of the project included constructing new roadway infrastructure, installing concrete pavement, building sidewalks and curb ramps, and completing stormwater intake improvements to support future development.
Purpose:
The project provides the infrastructure needed for future residential growth, creating new roadway connections and preparing the area for additional housing developments.
Impact:
The completed improvements establish the groundwork for a growing neighborhood while improving accessibility and supporting the City's long-term development plans. As future phases are completed, the new infrastructure will help connect residents and accommodate continued growth
in Altoona.
Reception & Results:
The first phase was completed successfully through strong coordination between Metro PCC, project partners, and the City of Altoona. The project represents the beginning of a larger development that will expand housing opportunities and support the community's continued growth for years
to come.
Every project starts with a conversation. Share the details, and our team will provide a clear, accurate quote to keep your work on track.
Request a Quote Request a Quote