Highway 63

Asphalt

Highway 63 overlays

Manatt's Newton Asphalt and Milling Division completed four different spot overlays at 2" and 3" in depth over the 8 mile long project. It took 10 total datys to complete 12,900 tons of HMA (Hot Mix Asphalt)

TAKEAWAY

The team stayed the course through multiple weather challenges